Hobbs
2041 hours logged overall Categories
Author Archives: pclifton
Finished drilling port h-stab
Got a late start tonight after going out for dinner with Josie. I did, however, get my angle drill in, so I was able to continue working right where I left off. First up were the tasks requiring the angle … Continue reading
Posted in Empennage
Hours Logged: 1.5
H-stab #2, drilling complete pending angle drill arrival
Short work night. Not because I’m busy, but because it didn’t take nearly as long as I thought to get to the point where I had to stop and wait for a new tool to arrive. Last night, I assembled … Continue reading
Posted in Empennage
Hours Logged: 1.5
Return to H-stab
In our last installment, I’d freshly mangled some additional sheetmetal while attempting to back rivet stiffeners to the rudder skin. Lest we forget, the whole reason I skipped ahead to the v-stab and then rudder was because I fouled up … Continue reading
Posted in Empennage
Hours Logged: 6.5
Back to work. And by work, I mean foul-ups.
*sigh* Obviously, work output on this project has gone down quite a bit. I’ve been out of town two of the past three weekends, with all the associated planning. Outside of that, now that it’s starting to heat up outside, … Continue reading
Posted in Empennage
Hours Logged: 1
Stiffeners!
Still here. Some busy times here, between some vehicular issues and going out of town this past weekend. I didn’t have a ton of time tonight, but I wanted to get out in the garage and do something. Luckily, I … Continue reading
Posted in Empennage
Hours Logged: 1.5
More rudder work
Short day in the shop-didn’t have a lot of free time tonight. Match-drilled the stiffeners to the skins, then removed them and deburred all the holes. There was also some more fun. As I was trimming the stiffeners last night, … Continue reading
Posted in Empennage
Hours Logged: 1.5
Skipping ahead again…this time to the rudder
So, as noted last time, I’ve been having some trouble with the front spar of the v-stab. Since then, I once again convinced myself that I could make those rivets good if I was really, really, really careful. So a … Continue reading
Posted in Empennage
Hours Logged: 4
Frustration
It had to happen sometime. The introduction section of the RV-8 preview plans contains this statement: “The project you are about to undertake will probably be the most frustrating, time-consuming, enjoyable, fulfilling, and rewarding you have ever experienced.” I knew … Continue reading
Posted in Empennage
Hours Logged: 4
V-stab rear spar done for real. Rest of the skeleton, not so much.
Short night in the garage today. I decided to wait on attaching the skin and just finish up the skeleton tonight. Finishing up the rear spar was a snap; all I had left to do was to rivet the VS-411 … Continue reading
Posted in Empennage
Hours Logged: 1
V-stab rear spar done…well, mostly
Yesterday, I said I hoped to get the v-stab skeleton done today. I did not achieve that goal, though I got pretty close. Still, I put in a solid day’s work on the project, and got my hands dirty with … Continue reading
Posted in Empennage
Hours Logged: 8.5